Microsoft's ERP Migration Agent Now Drafts the Requirements. UAT Has Always Tested Against Them.

Sharif George6 min read

An agent can now read a legacy ERP, draft the requirements for its replacement and propose the configuration. Microsoft is explicit that a person approves each step. UAT has always tested the build against the requirements, so the test basis is now the thing that arrives pre-written.

What Microsoft announced on 19 November

On 19 November, Microsoft published Move beyond legacy ERP and CRM with Dynamics 365 Activate, which states that "the ERP experience is now in private preview" while "the CRM experience for Salesforce migrations is now generally available". Two days earlier, the Ignite post introducing Dynamics 365 in Copilot named the same thing: Activate extended to ERP, starting with SAP ECC, in private preview.

Four stages are described. Discovery assesses configuration, customisations, integrations and dependencies, and infers processes from how people in each role work. Requirements turns that into business requirements and maps them to the Microsoft Business Process Catalog. Configuration proposes setup one process at a time, applying Success by Design practices. Migration maps master and transactional data to Dynamics 365 entities, then transforms, migrates and validates it. Microsoft's framing: "It can take on the heavy lifting from discovery through requirements, configuration, and migration, while your team reviews and approves every decision."

One figure deserves care. Microsoft says that in early CRM engagements Activate "has already processed more than seven billion records". That is a CRM number. The post gives no ERP equivalent.

The documentation still describes a Salesforce tool

The documentation has not moved with the announcement. The Dynamics 365 Activate overview on Microsoft Learn, last updated 9 September 2026, says that "Dynamics 365 Activate currently supports migration from Salesforce to Dynamics 365", and mentions neither ERP nor SAP ECC. It is still marked prerelease.

Announcement and availability are not the same event here: the blog announces an ERP private preview the documentation does not describe, behind a sign-up, with Microsoft's own footer noting that "Preview features aren’t meant for production use". None of it belongs on a client's critical path this quarter. What it changes is where the next requirements document comes from.

Requirements stop being written and start being approved

One sentence in the post describes the change to a test manager's job: "They can approve the requirements instead of starting from a blank page."

A blank page is slow, and it is also a forcing function. Someone has to decide what the business needs, write it down and defend it. What survives that argument is what a test case traces to. Replace it with a document to review and the slow part goes, along with the argument.

Microsoft is not blind to this. The configuration stage is framed around it: the team reviews each proposal before anything is applied, "so the solution reflects your decisions, not a one-for-one copy of the old system", and approved changes are versioned and auditable. That is a reasonable design, and it puts the control where Infor and Anthropic put theirs earlier this month: a person reading a summary and clicking approve. Reviewing a plausible document and authoring a contested one are different acts, and only one leaves a record of what was rejected.

What UAT is testing against now

User acceptance testing answers one question: does the system do what we said the business needs? The requirements are the test basis. Cases trace to them, and sign-off means a business owner agrees a requirement is met.

Derive those requirements from how the legacy system is configured and used, and a clean UAT cycle proves something narrower than it looks: that the new system reproduces the old one, including the workaround built around a limitation that no longer exists. None of that is a defect the agent introduced. Carrying the old process into the new system is the oldest failure in ERP implementation, and cheaper requirements make it easier to commit to at speed.

The second shift is traceability. A requirement approved in a batch may have nobody who can say what good looks like, and UAT needs exactly that person: not an approver of the document, but an owner of the outcome. Sign-off without a named owner is a date in a spreadsheet.

What belongs in the test plan

A named owner per requirement, recorded before approval. Not whoever approved the generated set, but the person who will sit in UAT and say whether the result is right. If no name fits, that is a finding about scope.

Cases written from intent, not from the generated text. A case derived from a requirement that was itself derived from the legacy configuration tests one assumption twice and calls the agreement evidence. Write the expected result from what the business wants, then compare it with the requirement.

A deliberate list of what you chose not to carry forward. An inventory of what the old system does is also an inventory of what the new one will not. Every deletion is an acceptance item, because somebody downstream will notice.

Data validation as scripted testing with its own evidence. Microsoft says checks built into the project plan can help catch data gaps and posting errors during the project, "not at your first month-end close", and that teams can stop maintaining mapping spreadsheets by hand and "focus on the exceptions that need judgment". Exceptions are where migration defects live, so the exception list is test evidence. Scope it like any other Dynamics 365 UAT workstream, and where the source is SAP ECC, keep the reconciliation of balances and open items on the SAP side scripted too.

The bottom line

A private preview you cannot yet put in front of a client is still worth reading, because it shows where the next requirements document will come from. LogicHive is UAT management software for ERP consultancies, MSPs and QA teams, and the discipline does not change when requirements arrive pre-written: an expected result stated before execution, a record of what ran, and a named owner against every acceptance decision. A generated document is not a test basis until somebody owns it.

→ERP is private preview and absent from the documentation. Salesforce CRM migration is generally available.
→Requirements you approve rather than write still need an owner by name, or sign-off has nothing behind it.

Free ERP UAT checklist (Excel)

A structured workbook covering the full UAT cycle: pre-UAT preparation tasks, test execution tracking, an issue log with severity guide, and post-UAT wrap-up. Built from real ERP implementations.

No spam. We will occasionally send UAT and ERP implementation resources. Unsubscribe any time.

Sources and further reading

Free Plan Available

Give Every Requirement an Owner

LogicHive gives ERP implementation teams scripted test cases with expected results, traceability from requirement to executed test, and a sign-off trail showing who accepted each result by name. When the requirements arrive pre-written, that trail is what turns them into something a client can accept. The free plan runs a real project end to end.

Written by Sharif George

Project Manager

Sharif is an experienced project manager, with years of project management experience behind him. At LogicHive he writes the ERP news roundups and the Business Central release coverage, following each Microsoft, SAP and Oracle change through to what it means for regression scope, acceptance testing and the project plan.

View all articles by Sharif George
  • ERP & Enterprise

    Microsoft Moved Sustainability Into the ERP Portfolio. No UAT Plan Has a Tester Who Can Sign Off a Carbon Number.

    On 3 November, Microsoft's Chief Product Officer for Dynamics 365 Finance, Human Resources and Sustainability wrote that “we are welcoming Microsoft Sustainability Manager into the Dynamics 365 ERP portfolio”. No feature in the post carries a preview or general availability date, and the green ledger view it describes was already listed in the 2026 wave 1 release plan, so the announcement consolidates ownership rather than shipping anything. What it does change is scope. Emissions figures are produced by configured calculation models: conditional logic, estimation factors, emission factor libraries and custom Power Fx with documented gaps. They fail by returning a plausible number rather than an error, and on a typical ERP project nobody is nominated to approve them.

    9 November 2026 · 5 min read

  • ERP & Enterprise

    Dynamics 365 Release Waves Are Ending: What That Does to Your Regression Testing Calendar

    Microsoft is retiring the twice-yearly release wave model in favour of continuous publishing, and the Release Planner retires on 15 November 2026. Business Central still updates on schedule, but the planning checkpoint most partners used as their regression testing calendar has just gone.

    12 September 2026 · 5 min read

  • ERP & Enterprise

    Business Central 2026 Wave 1: What AI Agents Mean for Your UAT Process

    BC 2026 wave 1 ships AI agents and an MCP Server that lets them post documents autonomously. Here is what that means for UAT on your next Business Central implementation.

    7 April 2026 · 10 min read