Business Central 29 Ships in October Without a Release Plan: How to Scope the Regression Pass

Sharif George6 min read

Business Central 29.0 becomes generally available in the first week of October. It arrives without a release plan: Microsoft confirmed there would be no September 2026 release wave 2 announcement, so the planning document most partners quietly used as the scope for their upgrade regression pass was never written.

What changed this month, and what did not

Microsoft's partner announcement of 4 September is unambiguous. Roadmap content for Dynamics 365, Power Platform and Dataverse is moving to the AI at Work roadmap, and, in the announcement's own words, "there won't be a September 2026 Release Wave 2 announcement. Instead, Microsoft will archive Release Plans on Microsoft Learn and retire Release Planner by November 15, 2026."

The Business Central documentation says the same from the product side: from September 2026 Microsoft stops publishing Release Plans, new capabilities go to the AI at Work roadmap, and features are no longer linked to release plans at all.

That is a change to how updates are announced, not to how they ship — and the distinction is the whole story for anyone running a test cycle.

The update still arrives on the old schedule

Coverage since August has blurred the two, leaving the impression that Business Central itself is going continuous. It is not. Microsoft put it plainly when it announced the roadmap move: the transition "changes how Microsoft communicates upcoming innovation. It doesn't change how our products are built, released, or deployed."

The mechanics are unchanged:

→Two major updates a year, in April and October, generally available around the first working day of the month.
→A five-month update period. An October release can be scheduled anywhere inside it, which puts the back wall in early March.
→Update windows still apply. Default 8:00 PM to 6:00 AM local, minimum six hours. An update that does not finish inside it is cancelled, rolled back and rescheduled seven days later.

The deadline your customers face in October is the one they faced last October. What has gone is the artefact you planned against. We covered that shift when the release wave model was retired; 29.0 is where the consequences land.

Where the feature list lives now

Two sources replace it, and they are not equivalent. The "What's new or changed" article for update 29.0 on Microsoft Learn is the closer substitute and the better one for testing: dozens of entries across development, finance, supply chain, reporting and Copilot, tied to a version number rather than a wave. The AI at Work roadmap is the forward-looking feed — items moving through In Development, Rolling Out and Launched, filterable by product and exportable to CSV.

A roadmap built around always-on publishing tells you what is coming. It does not give you a bounded, dated list of what is in the version landing on a given tenant next month. Rebuilding that list is partner work now. Under the wave model the job had a natural twice-yearly rhythm; under continuous publishing it has none, which in most partner businesses means it quietly becomes nobody's.

The list you actually need is the deprecation list

Feature announcements rarely break a live customer; removals do. The deprecated-features pages on Microsoft Learn sit outside both the release plans and the roadmap, and were never part of the wave announcement anyway. Version 29 removing SOAP on Microsoft UI pages is this wave's example: no screen changes, no headline, and an EDI feed stops.

Your preview sandbox has a deletion date

The 29.0 preview has been available in sandbox environments since the first week of September. Microsoft's documentation also states that it automatically deletes preview sandboxes 30 days after 29.0 goes generally available — early November 2026.

This catches teams out every wave. A partner spins up a preview sandbox, runs a partial regression pass, logs a few defects, and plans to finish once the customer's own upgrade is scheduled in January. By then the environment is gone, along with the test data and configuration that made the results meaningful. Evidence of a pass that lives inside the sandbox expires on the same schedule.

Scoping a regression pass without a release plan

The release plan was always a weak basis for scope: it described what Microsoft built, not what your customer uses. Losing it is an argument for scoping the way it should have been all along.

Anchor the pass to the version, not the announcement. The trigger is "this tenant is scheduled for 29.0 on this date", taken from the admin centre — a fact that still exists and is still dated, which is more than the roadmap gives you.

Build the scope from the customer, then check it against the version. Start with the processes that stop the business if they break — order to cash, the month-end close, the integrations, the reports finance actually opens — and run those every wave regardless of what Microsoft shipped. Then read the deprecation list and the 29.0 article for anything touching them. Reading the release plan first tended to produce a test pass shaped like Microsoft's backlog.

Keep a reusable regression suite per customer. Rebuilt from scratch each October, the missing release plan is a real problem. Maintained and topped up with version-specific cases, it is an inconvenience. Our Business Central UAT guide covers how to structure one, and what separates regression from acceptance testing is worth settling before October.

The bottom line

Nothing about October got harder; the planning input got worse. The teams that feel it are those whose regression scope was borrowed from Microsoft's paperwork rather than built from their customers' processes.

→29.0 is generally available in the first week of October. There is no 2026 release wave 2 plan, and Release Planner retires on 15 November 2026.
→Announcement cadence changed; shipping cadence did not. Still two major updates a year, April and October, with a five-month update period.
→Use the version's "What's new or changed" article and the deprecation pages for test scope. The roadmap is for adoption planning.
→Preview sandboxes are deleted 30 days after GA, around early November. Keep test evidence somewhere that outlives the environment.

Free ERP UAT checklist (Excel)

A structured workbook covering the full UAT cycle: pre-UAT preparation tasks, test execution tracking, an issue log with severity guide, and post-UAT wrap-up. Built from real ERP implementations.

No spam. We will occasionally send UAT and ERP implementation resources. Unsubscribe any time.

Sources and further reading

Free Plan Available

A Regression Suite That Outlives the Sandbox

LogicHive gives Business Central partners a reusable acceptance pack per customer: structured test cases you top up each version rather than rebuild, named assignment, linked defect tracking and sign-off evidence that survives the environment it was run in. The free plan runs a real project end to end.

Written by Sharif George

LogicHive Frontman

Sharif is the frontman for LogicHive. He writes the ERP news roundups and the Business Central release coverage, following each Microsoft, SAP and Oracle change through to what it means for regression scope and acceptance testing on live implementation projects.

View all articles by Sharif George